In mid-2024, GujRERA had the bank accounts of around 1,000 developers frozen for failing to meet quarter-end compliance, according to Housing.com. Most of these were not fraud cases. They were developers who missed progress reports, did not report completion, or did not apply for extensions in time.
Here is the part that is easy to miss: almost every RERA filing depends on information that comes from the construction site. Percentage of work completed, engineer certificates for fund withdrawals, revised timelines, as-built records. If your construction partner cannot deliver that information on time and in the right form, the compliance risk lands on you, the promoter.
This guide explains the RERA obligations that depend on construction, and the specific deliverables you should write into your construction contract.
Which Projects Must Register With GujRERA?
The RERA Act applies to commercial projects as well as residential ones. If you are building offices or shops to sell, registration on the GujRERA portal comes before any marketing. A developer who builds to lease out the entire asset does not sell units and usually sits outside RERA, but should confirm this with a consultant for the specific structure.
The RERA Obligations That Depend on Your Construction Partner
| RERA obligation | Section | What the developer needs from the construction partner |
|---|---|---|
| Keep 70% of buyer receipts in a separate account; withdraw in proportion to completion | 4(2)(l)(D) | Engineer-certified percentage of completion and cost incurred, supported by measurement records |
| Update project progress every quarter | 11(1) and GujRERA regulations | Stage-wise progress data, photos and revised schedule each quarter, on a fixed date |
| Build as per sanctioned plans and specifications | 14(1) and 14(2) | No deviation without written instruction; a variation register linked to approvals |
| Complete by the declared date | 18 | A realistic baseline schedule and early warning of delays |
| Rectify defects for 5 years after possession | 14(3) | Back-to-back defect liability, as-built drawings and quality records |
1. Quarterly Progress Reports (QPR)
GujRERA’s 2024 amendment regulations replaced the earlier Forms 1, 2 and 3 with a single Form 8, which promoters can submit directly. The simplification makes timely reporting easier, but it also removes excuses. The data still has to be accurate, and it still comes from the site.
Write these into your construction contract:
- A monthly progress report in a format that maps directly to the RERA stages of your project (excavation, foundation, each slab, masonry, finishes, services, external works).
- Date-stamped site photographs for each reported stage.
- Delivery of quarter-end data at least 7 days before the filing deadline, so your team has time to review.
- A named contractor contact responsible for RERA data.
2. Withdrawals From the 70% RERA Account
This is where weak site documentation turns into a cash-flow problem. If your engineer cannot certify progress because measurement records are incomplete, money stays locked in the RERA account while the contractor waits for payment. We covered how payment delays feed cost overruns in our cost overrun guide.
What to require from the construction partner:
- Measurement books and bills that reconcile with the BOQ, so certified progress and billed progress match.
- A monthly cost-to-date statement in the same structure as the project’s estimated cost declared to GujRERA.
- Cooperation with the project’s certifying engineer and architect for site verification.
3. Building Strictly to Sanctioned Plans
Small site decisions can quietly create RERA exposure: shifting a staircase, changing a specified material, enlarging a common area. Each of these may need a revised development permission under CGDCR and, for many changes, buyer consent.
- No deviation from approved drawings without a written instruction from the developer.
- A variation register that records each change, the reason, the approval status and its cost and time impact.
- Material substitutions only with the developer’s written approval, checked against the specifications disclosed to buyers.
4. Completing on the Declared Date
The completion date you declare to GujRERA should come from a construction schedule you trust, with buffers for approvals, monsoon and procurement. Our delay-proof scheduling framework explains how to build one. If the date must move, GujRERA’s extension process has to be started before the registration lapses. The 2024 account freezes show what happens when it is not.
- A baseline programme agreed before RERA registration, not after.
- Monthly schedule updates with a clear forecast completion date.
- Early-warning notices for any event likely to delay completion by more than an agreed number of days
5. The 5-Year Defect Liability Gap
This is the most common gap we see in construction contracts reviewed by developers. The promoter carries a five-year statutory obligation, while the contractor’s liability ends after a year. Close the gap in the contract:
| Contract term | Typical clause | RERA-aligned clause |
|---|---|---|
| Defect liability period | 12 months from completion | Structural warranty aligned to the RERA period, plus a defined DLP for finishes and services |
| Security | Retention released at DLP end | Part retention or a bank guarantee held for longer, or a warranty bond |
| Response time | Not defined | Attendance and rectification within a time that lets the developer meet the 30-day statutory window |
| Records | Not required | As-built drawings, material test records and quality reports handed over at completion |
Quality records are your best defence if a buyer raises a defect claim. Our guide to quality tests at each construction stage lists what to collect. If you are choosing between contract structures, see our comparison of lump sum, item rate and cost-plus contracts.
Common RERA Gaps in Construction Contracts
- Generic progress reports that describe activities rather than RERA stage completion, so the promoter’s team has to re-work them every quarter.
- No data deadline, which pushes reporting to the last day and leaves no time to check numbers.
- BOQ structure that does not match the declared project cost, making it hard to prove that withdrawals match work done.
- Verbal site instructions that change specifications without a record, creating exposure under Section 14.
- Short defect liability with full retention released after 12 months.
Each gap is easy to close during contract drafting and expensive to close after a buyer complaint or a GujRERA notice.
Penalties for Getting It Wrong
| Default | Possible consequence |
|---|---|
| Selling or advertising without registration | Penalty up to 10% of estimated project cost (Section 59) |
| Other contraventions, including reporting failures | Penalty up to 5% of estimated project cost (Section 61) |
| Late quarterly reports in Gujarat | Daily late fee from January 2025, scaled to project size |
| Registration lapsed without extension | Account freeze and restrictions on booking unsold units |
| Delay in possession | Interest to buyers for every month of delay (Section 18) |
Construction Partner RERA Deliverables Checklist
- Monthly progress report mapped to RERA stages, with photographs.
- Quarter-end data delivered at least a week before the filing deadline.
- Measurement records and bills that match the BOQ and the declared project cost structure.
- Support for the engineer, architect and CA certifying withdrawals.
- A variation register; no deviation without written instruction.
- A baseline schedule agreed before registration, updated monthly.
- Defect liability and security aligned with the five-year RERA obligation.
- As-built drawings and quality test records handed over with the building.
Use this list alongside our broader contractor evaluation checklist when shortlisting partners.
Working With Brahmani Buildcon on RERA Projects
Brahmani Buildcon brings 35+ years of experience, 55+ projects and 20+ million sq ft developed across Gujarat. Explore our commercial projects.
Frequently Asked Questions
Does RERA apply to commercial projects in Gujarat?
Yes. Commercial projects where units are sold must be registered with GujRERA, unless they fall under an exemption such as land up to 500 sq m or up to eight units.
How often must developers update GujRERA?
Project progress must be updated every quarter. Since January 2025, Gujarat uses Form 8 for this and applies a daily late fee for delayed filings.
What is the 70% rule under RERA?
Seventy percent of the money received from buyers must be kept in a separate project bank account and used only for land and construction costs, with withdrawals in proportion to completion certified by an engineer, architect and CA.
How long is defect liability under RERA?
Five years from possession. The promoter must fix reported structural, workmanship, quality or service defects within 30 days at no cost to the buyer.
Can a developer change approved plans after RERA registration?
Minor alterations are allowed with disclosure. Other changes need the written consent of at least two-thirds of the allottees, plus a revised approval from the planning authority.